SNS Economic Policy Council Report 2022: Public Procurement

1/20/22

A major problem with regard to public procurement is that buyers are not allowed to take previous experiences with suppliers into account when evaluating tenders. In order to remedy this, the SNS Economic Policy Council proposes introducing rating systems for suppliers to the public sector similar to systems used online to rate taxi and hotel services.

In 2019, Swedish public sector procurement amounted to more than SEK 800 billion, corresponding to almost 18 percent of GDP. In the SNS Economic Policy Council Report 2022: Public Procurement, the authors highlight a number of problems related to how public procurement is currently carried out while also suggesting ways of addressing these.

past performance is not taken into account

First, current procurement rules limit the possibility of using information on previous deliveries when carrying out evaluations in a new tender process.

“It is difficult to prevent a supplier that has previously misbehaved from participating in a new tender process. And it is even more difficult to reward a supplier you are satisfied with. Furthermore, it is not possible to include information on other organizations’ experiences with a supplier in the evaluation, other than in the form of references,” says Sofia Lundberg, professor of economics at the Umeå School of Business, Economics and Statistics, Umeå University and chair of the SNS Economic Policy Council 2022.

In order to remedy these problems, the researchers propose introducing rating systems for public sector suppliers that take past deliveries into account, similar to the online services used for rating, for instance, taxi and hotel providers.

weak link between price in tender and price in contract

Second, there may be a weak link between tender price and what is actually paid out, which, according to the researchers, risks ruining the entire tender procedure.

“If the tender price repeatedly differs from what is actually paid, there is no reason for suppliers to submit bids reflecting the actual costs. This increases the risk of dishonest suppliers winning contracts,” says Mats Bergman, professor of economics at Södertörn University.

The researchers believe that government authorities need to get better at designing their procurement processes so that the price in the winning bid more clearly reflects the actual money paid out.

inadequate division of responsibility for cost overruns

Third, uncertainty regarding costs is not handled properly. It is difficult to know in advance how much a complex service such as constructing a building or bridge will ultimately cost. Surprises in the form of, for instance, difficult ground conditions and bad weather affect both costs and quality. That is why contractual terms and follow-up procedures play a crucial role.

“We can offer examples of shortcomings in both contracts and follow-ups. There are cases indicating that somewhere between the call for tenders and the final delivery, the procurement process goes from a fixed-price contract to a cost-plus contract. In some cases, the amount paid out is three or four times higher than the tender price,” says Malin Arve, associate professor of economics at the Norwegian School of Economics.

The researchers recommend that potential cost overruns should be managed in the contract as far as possible in advance (e.g., by cost-sharing contracts). This reduces the risk of unjustifiably high amounts being paid out and increases the level of predictability for the buyer.

authors

Sofia Lundberg (chair), Professor of Economics, Umeå School of Business, Economics and Statistics, Umeå University

Malin Arve, Associate Professor of Economics, Norwegian School of Economics, Bergen

Mats A. Bergman, Professor of Economics, Södertörn University

Lars Henriksson, Professor of Law, Stockholm School of Economics

More from SNS Economic Policy Council

Other research report on Public Finance

  • A Swedish Tax System for the 21st Century

    Reduce the tax on labor, introduce a uniform VAT and a uniform taxation of capital income. This is proposed by economist Åsa Hansson in a new SNS report. Much has changed since the major tax reform of 1990–91. If the tax system is reformed on the basis of current conditions, she argues, Sweden can achieve higher growth and employment.
  • Local Taxation and Economic Incentives

    Swedish municipalities and regions have incentives to raise taxes more than what is optimal from society’s point of view, according to economists...
  • The Swedish Dual Income Tax System and the Splitting Rules Yesterday, Today, and in the Future

    Search Public Finance Tax scholar: “We should consider introducing 3:12 rules based on the Finnish model” Press releases 2021.09.08 All press releases The so-called 3:12 rules play a crucial role in the taxation of labor and capital incomes. However, different marginal tax rates for labor incomes and dividends do not necessarily have to constitute a problem if the 3:12 rules are well-designed. This is argued by economist Håkan Selin, author of the SNS report The Swedish Dual Income Tax System and the Splitting Rules: Yesterday, Today, and in the Future.
  • How Should Consumption Be Taxed?

    Higher taxes on consumption combined with lower taxes on labor would benefit the economy in a number of ways. This is argued by tax scholar Spencer Bastani in a new SNS report in which he, among other things, proposes a unification of VAT rates and a broadened VAT base.

Subscribe to our Newsletter

Stay updated with our latest insights, seminars and research news.